Second slag-cleaning furnace for Anglo Platinum? 28th January 2008
Anglo Platinum may take a second slag-cleaning furnace after the introduction of the platinum industry's first model in 2003.
Speaking to miningweekly, Hugo Joubert, Executive Manager for Sales and Marketing at Tenova Pyromet, said: "There is only one slag-cleaning furnace in operation in the platinum industry at the moment, with another being built.
"No one else has done a slag-cleaning furnace for the platinum industry before," he added.
A feasibility study for a second unit is being undertaken and Mr Joubert is hopeful that Anglo Platinum will take another.
"We believe our trademarked Maxicool sidewall copper-cooling system, our patented electrode column and copper-launder system, as well as our furnace shell and feed system, give us a strong competitive advantage," he added.
Base metals and platinum-group metals (pgm) can be recovered from the slag-cleaning furnace at the Waterval Smelter.
"Higher and higher levels of chrome in the converter slag result in build-up in the primary smelters. The use of a slag-cleaning furnace is preferential in order to avoid transferring the chrome back into the primary smelters," explained Mr Joubert.
Source:
Slag-cleaning furnace only one of its kind in platinum industry, 25/01/08
http://www.miningweekly.co.za/article.php?a_id=123486
Ÿ Adfero Ltd

Bookmark Using:
Send by email Share on Facebook Tweet this LinkedIn Digg it Bookmark with Delicious Subscribe to Feed Print this page